HRT #3
- Length repaired
- 23 m
- Epoxy mortar
- ~375 MT
- Done in
- 36 days
- Target
- 45 days
- 100–125 workers, round the clock
- Material moved 700 m through the tunnel by hand
Eight jobs at India's tallest dam: dredging the Bhagirathi below the spillway, walling it, and repairing the tunnels and intakes that feed 1,000 MW.
Tehri HPP (1,000 MW) and Tehri PSP only stop for short, scheduled shutdowns. Each CPS job had to fit inside one.
Below the dam the Bhagirathi rose and fell 8–10 m twice a day, leaving 3–4 hours of working time per shutdown. Inside the tunnels the only access was a crane down a 100 m surge shaft.
Feb – Jul 2023Zero schedule of Tehri HPP
Dredging across 640 Rm of the Bhagirathi downstream of the spillway, done while the river level swung 8–10 m twice a day.
Feb – Jul 202347 m across the Bhagirathi
A baffle wall about 47 m long across the river between the spillway and the TRT of Tehri HPP, poured under water onto a micro-piled, saturated riverbed.
Jun – Jul 2024A 35-day shutdown
The second phase dredged 1,50,000 cum and built 70 m ramps either side of the baffle wall, all inside a 35-day shutdown and through monsoon rain.
Jun – Jul 202414,400 cum concreted
Ramps 70 m long and 5 m wide along the Bhagirathi, piled and poured under water in the same shutdown.
HRT #3 and #4Tehri PSP, 8.5 m diameter
Repairing the 8.5 m head race tunnels meant lowering every worker and every bag through the surge shaft by crane, then moving the epoxy 700 m along the tunnel by hand.
Tehri PSPSeepage control
Specialised drilling and grouting through the drainage galleries of Tehri PSP: stabilisation and seepage control done with very little room to move equipment.
Shafts T1 to T4Four months
Repair of the swirling-device bottom in all four surge shafts, with water falling continuously from 150–160 m above. A 25 m scaffold went up inside each 16 m shaft and the water was funnelled away from the work.
31 May – 14 Jun 202516 days against 30 planned
Epoxy treatment at Intake Structures 1 and 2, EL 745 m, Tehri HPP. Planned for 30 days, handed over in 16.
2.5 lakh cum
dredged across phases 1 and 2 and hauled 14 km
805 MT
of epoxy mortar in HRT #3 and #4, both inside the 45-day target
16 days
for the intake epoxy treatment, planned for 30
Every CPS site has its own window, river and rock. Pick the next one.
Discuss a project