Multiple phases of critical work at Tehri HPP (1000 MW) and Tehri PSP — including river dredging of the Bhagirathi River, construction of a 47m baffle wall, HRT/TRT tunnel repair with epoxy mortar, micro piling, drilling & grouting, and epoxy treatment at intake structures.
River dredging across 640 Rm of the Bhagirathi River downstream of Tehri Dam spillway — executed during zero schedule of Tehri HPP. Water level varied 8-10m twice daily, with only 3-4 hours of working time per shutdown.
River dredging operations
Water level at 604+ MTR
Excavation in variable water
Dredging March 2023
Heavy machinery deployment
Water level 603.75 MTRConstruction of approx 47m long Baffle Wall across the Bhagirathi River between Spillway & TRT of Tehri HPP (1000MW). Underwater concrete pouring, micro piling in saturated riverbed conditions.
Baffle Wall construction
Micro piling operations
Concreting in progress
Wall segment formation
Foundation reinforcement
Completed Phase 1 baffle wallThe second phase involved dredging 150,000 Cum from Chainage 260m to 660m and construction of Ramps (5m wide, 70m long) upstream & downstream of the Baffle Wall — all within a strict 35-day shutdown window.
Phase 2 dredging operations
Excavation in progress
River bed operations
Machinery at work
Dumper loading operations
Approach constructionConstruction of 70m long, 5m wide Ramps upstream & downstream along the Bhagirathi River. Micro Piling (850m) in foundation. All carried out during the 35-day shutdown with underwater concreting via Boom Placer.
Ramp construction
Concreting by Boom Placer
Underwater concrete pouringRepair of 8.5m diameter Head Race Tunnels (HRT #3 and #4) at Tehri PSP via surge shaft at 100m vertical depth — involving massive quantities of epoxy mortar, underwater repair, and custom engineering solutions.
TRT/HRT repair work
Epoxy mortar in HRT #3
Material through trolley
HRT #4 plug breaking area
Foundation epoxy work
Tunnel repair operations
TRT tunnel preparations
TRT surface preparation
TRT epoxy applicationSpecialized drilling and grouting works were performed throughout the Drainage Gallery networks at the Tehri PSP. This critical stabilization and seepage control measure was executed despite heavily restricted tunnel access and spatial constraints.
Drilling & Grouting OperationsRepair of the swirling device bottom area in all four tunnel surge shafts. Faced with continuous waterfalls dropping from 150-160m heights, a spectacular engineering feat was executed: a 25m tall scaffolding was built inside the 16m diameter shaft. Water was funneled away using completely customized GI sheets, enabling full epoxy treatment, mortar seals, and fiberglass cloth wrapping of the shaft walls over 4 stipulated months.
Custom Scaffolding & Water FunnelEpoxy treatment at Intake Structures 1 & 2 at EL 745m of Tehri HPP. Work proposed for 30 days but completed in just 16 days (May 31 – Jun 14, 2025).
Intake structure epoxy work
Construction joint treatment
Completed intake repairTotal material dredged across Phase 1 & 2, transported 14km in adverse conditions
Consumed in HRT #3 & #4 repair — both completed ahead of 45-day schedule
Intake epoxy treatment completed in 16 days vs 30-day target — 47% early